EU EPBD solar-installation deadline: existing public buildings above 2,000 m²
Directive (EU) 2024/1275 requires Member States to ensure the deployment of suitable solar energy installations on existing public buildings with a useful floor area larger than 2,000 m² by 31 December 2027, where technically suitable and economically and functionally feasible. Article 10 contains separate thresholds and dates for other building categories.
Record
- Jurisdiction European Union
- Category Solar, Mobility and Building Technology
- Legal stage published
- Binding status binding_eu_law
- Effective date 2024-05-28
- Next milestone Solar-installation deadline for existing public buildings above 2,000 m² — 2027-12-31
- Legally verified 2026-10-19
- Source Directive (EU) 2024/1275, Article 10 (EUR-Lex)